A Texas town has said yes to an 88-acre data center that will sit about 500 feet from the backyards of homes in the neighboring city. The Westlake Town Council voted 5 to 1 on Thursday, November 12, 2026, to approve the project after months of litigation.

The vote came with a settlement that adds noise limits, screening and $1.8 million in funding tied to monitoring and emergency response. The vote was covered by the Fort Worth Report.
Council Approves The Deal 5 To 1, With A Settlement Passed Unanimously
Council members approved a development agreement with PowerHouse Data Centers, the developer leading the Circle T project off U.S. 377. The 88-acre site is inside Westlake’s boundaries but only about 500 feet from the backyards of Keller residents.
The deal was first set for approval in August, but a temporary restraining order barred the council from moving forward. The council also voted unanimously to approve a settlement agreement among Westlake, the city of Keller, the data center developer and residents of the homes next to the site.
Keller’s city council had approved the settlement unanimously the week before.
Neighbors Learned Of The Project From Social Media
Westlake officials announced the project online on July 29. In early August, several Keller residents said they felt blindsided after learning about it through social media.
The site’s closeness to Keller homes became a flashpoint, since Westlake officials had promised the data center would be at least 1,200 yards from Westlake homes. A Fort Worth district judge blocked the project with a temporary restraining order requested by the Lakes at Marshall Ridge Homeowners Association, which represents the adjacent Keller neighborhood.
The city of Keller quickly joined the lawsuit. Mayor Ross McMullin said in a statement last week: “Keller’s first responsibility has been, and will always be, to protect our residents. Throughout this process, we have fiercely advocated for our residents, especially those living closest to the proposed data center site.”
The Settlement Sets Noise Limits And A 10-Foot Berm
The settlement sets standards meant to protect quality of life for Keller residents. It gives Keller enforceable rights to monitor and address noise, screening and operational conditions.
It sets daytime and nighttime noise limits at residential property lines. It also requires an independent baseline noise study and quarterly noise monitoring for three years after the data center begins operating.
The data center must be separated from Keller homes by a 10-foot landscaping berm, and trees that are damaged or die along the screening line must be replaced.
Where The $1.8 Million Goes: $1.5 Million To Monitoring, $300,000 To Firefighters
Of the $1.8 million, $1.5 million is for noise monitoring and evaluating environmental impact. The other $300,000 goes to Keller Fire-Rescue for training, equipment, decontamination and other costs tied to the data center, according to a Keller news release.
The development agreement adds more. PowerHouse must pay Westlake $914,000 to renovate the town’s pump station next to the site, which manages water distribution.
The agreement sets aesthetic standards, including stone materials on accessory buildings and screening walls to hide mechanical equipment from public view. The developer paid for a 350-megawatt substation built by Oncor on the west side of town to power the data center, and Westlake says on its website that the data center will not increase electric rates.
Mayor Kim Greaves said last week that the developer paid all costs associated with litigation over its project.
Westlake Counts On $5 Million A Year In Tax Revenue
The town estimates Circle T will contribute about $5 million a year in tax revenue during its first 10 years of operation and $7 million a year after that. Officials say the 14 percent increase in revenue to the town’s budget will support essential services, infrastructure improvements and long-term property tax stability.
Westlake says the site is privately owned land zoned for commercial and industrial use since 1998. The neighboring Keller area was also zoned for such use until 2006, when Keller’s council changed the zoning to allow homes.
A town web page states: “While Keller’s zoning for their property changed, Westlake’s vision of the adjacent land within our town limits has not.”
Westlake has about 1,900 residents (2023 estimate) and a median household income of $250,000, which makes it one of the wealthiest cities in Texas. Greaves thanked the developer: “I want to thank PowerHouse for being an outstanding partner throughout this process. Their team listened to the homeowners and to Keller’s leadership, stayed at the table and worked towards a resolution.”
“Data Centers Are Going To Be Important. I Just Don’t Think They’re Important For Our Town”
Council member Michael Yackira, a former electric company CEO, cast the no vote. He said he understood the data center would be a “financial boon” for Westlake, but after three months of reflection he could not in good conscience vote yes.
“Data centers are going to be important. I just don’t think they’re important for our town,” he said. He worries the booming industry will push up electricity rates across Texas.
Tri-County Electric Cooperative has exclusive rights to serve Westlake, so residents cannot shop for a cheaper provider. Yackira proposed that PowerHouse put money into a reserve fund to cover any rate increase for Westlake residents.
PowerHouse executive Jeff Parsons answered: “I apologize. I’m not in a position where we could afford a fund like what you described.”
What Homeowners Near A Data Center Plan Should Do
Data centers are being proposed near homes across the country, and this case shows a town that stands to gain millions in revenue facing neighbors in another city. The settlement puts enforceable limits in writing.
If a project like this is proposed near you, check zoning maps and the agenda for town and city council meetings early. Ask for noise studies, screening plans and the distance from your property line in writing.
Neighbors can organize through their homeowners association, and a settlement that spells out noise limits, monitoring and penalties gives residents something to enforce. The lone dissent raised electric rates, a concern that sits outside the agreement, so ask your utility how a new large customer could affect your bill.
More Stories You May Like
- Excavator Operator Returns To A Nightmare Site To Drop A 1,000 Gallon Drivable Septic Tank 20 Feet From The House, Then Bridges A Soft Trench With Two Feet Of Sand In Pouring Rain
- Unlicensed Contractor Who Told Customers He Was Licensed Is Banned From Minnesota Construction For Good And Hit With A $1.1 Million Judgment After Faking A Supplier Invoice
- Son Secretly Fixes Up A House For 10 Months And Hands It To His Mom, Who Had Been Renting Her Whole Life And Had No Idea Until She Walked In
Leave a Reply